Finished oak framed double garage on a misty morning, waney edge cladding and ledged barn doors

An oak framed garage with barn doors, in the Surrey Hills

We did the carpentry on this green oak double garage as part of a garden project run by Radial Landscapes. Work started on 27 November 2023, and in about a week the frame went up, the roof was cut and slated, and the garage was finished with waney edge oak boards, ledged barn doors, a side door and a storage mezzanine.

Where
Surrey Hills
On site
November to December 2023
Our role
Carpentry within Radial Landscapes' garden project
Work
Oak frame raising, cut roof, slating, cladding and fit-out

The finished garage on a misty morning, December 2023.

A garage built into someone else's garden design

This garage sits in a large garden in the Surrey Hills, at the end of a new herringbone clay paver drive, near an old Victorian-style glasshouse. The whole garden was being remade by Radial Landscapes to a garden designer's plan, and the oak garage was one part of it. The drive, the patio and the brick planters round the garage were part of Radial's landscaping, not our work.

Our part was the carpentry. The garage is a double green oak frame on a brick plinth: oak posts, curved braces and a long tie beam carrying a softwood cut roof, with oak boarding outside and plywood lining inside.

We keep the exact address private.

Front of a new oak framed double garage with ledged oak boarded doors and black strap hinges
The front of the garage at the end of the new drive, December 2023.

One week, from oak on bearers to barn doors

Day one was 27 November 2023. By 2 December the garage was finished. These are the stages from our posts that week.

  1. Day one: the frame goes up

    Us

    The oak arrived on bearers. We lifted the posts and beams onto the brick plinth with a compact loader, then braced up the softwood stud infill panels in the rain. By the end of the day the frame was standing, with its curved braces and tie beam in place.

  2. Pegging the joints

    Us

    Two of us worked in tandem from a board, driving oak pegs into the post and beam joints with a mallet. In a traditional oak frame, the pegged joints are what hold the frame together, so every one gets driven home by hand.

  3. The cut roof

    Us

    On 28 November the rafters went up from the scaffold deck. Then the breathable membrane was rolled out, lapped and taped, and the counter battens and slate battens fixed over it. By that evening one of us was sat up on the battened roof.

  4. Slating in the frost

    Us

    Cutting went on under a gazebo by the scaffold, and the first courses of Tapco synthetic slate went on along the eaves on 29 November. The slates climbed the roof from there, and the roof was finished on a frosty morning at minus one.

  5. Boards, doors, lining and mezzanine

    Us

    By 2 December the garage was clad in waney edge oak weatherboard, with ledged and braced barn doors on black strap hinges, an oak side door in the gable, plywood lining between the posts inside, and a mezzanine floor for extra storage.

Building in oak through a wet, freezing late November

The weather was the hard part of this one. Day one was raining while the frame went up and the stud panels were braced. By the end of the week it was below freezing, and the slating was finished on a roof white with frost. We set the saw up under a gazebo and kept going.

Green oak doesn't mind the wet, but it shows it. The fresh oak side door picked up dark water and tannin marks in the first days, which is normal for new oak and fades as it weathers. The boards will go the same way, from the honey colour in these photos towards silver grey over the years. That's what people choose oak for, and it's worth knowing before you choose it.

Corner of an oak garage with waney edge weatherboards, a corner post and a ledged oak door
The corner post, gable door and waney edge boards, December 2023.

The roof going on, and the whole build in one reel

Rafters, membrane and battens 28 November 2023. The cut roof going onto the oak frame: rafters set from the scaffold deck, breathable membrane rolled out and the battens fixed.
Frame to finished garage Posted with Radial Landscapes in December 2023. The frame going up, the roof and slates, then the finished garage at the end of the new drive.

Awesome week. Oak frame with barn doors and side door, ply lined and a mezzanine floor for extra storage.

Our Instagram, 2 December 2023

Thinking about an oak garage or cart lodge?

Send us a few photos of where it would go and a rough idea of size. Tell us if a landscaper or designer is already involved, because we're used to fitting our part round theirs. We'll come back with how we'd build it and what we'd need to see.

Useful to send

  • Photos of the spot, and of the house it will sit beside
  • Rough sizes, and how many bays you want
  • Your town or postcode