The difference in one sentence

Planning permission is about what you build and where; Building Regulations are about whether it's built safely and properly. That's the whole difference, and almost every mix-up we hear comes from treating one as if it were the other.

They come from different laws and go to different people. Planning sits under the Town and Country Planning Act 1990 and is decided by your council's planning department. Building Regulations sit under the Building Act 1984 and the Building Regulations 2010, and are checked by a building control body, which can be the council's own team or a private firm. A yes from one tells you nothing about the other.

Two examples make it clear. A single storey rear extension inside the permitted development limits needs no planning application, but it does need Building Regulations approval. Knocking out a load-bearing wall between your kitchen and dining room is the other way round: no planning, because it's inside, but full Building Regulations, because it's structural. If you're weighing up a job like either of those, our building work page explains how we run them.

What does planning permission cover?

Planning controls development, which the law defines as building operations, engineering work and any material change in how land or a building is used. It's about the outside and the use: how big something is, how it looks, what it does to the neighbours' light and privacy, the trees, the parking, the street.

Work that only affects the inside of a building, or doesn't materially change how it looks from outside, isn't development at all (section 55(2)(a) of the 1990 Act). That's why a new kitchen, a knock-through or a loft fit-out with no new dormer doesn't need planning permission, unless the house is listed.

A lot of householder work is permitted development: planning permission granted nationally by the General Permitted Development Order 2015, so long as the job stays inside its limits. Most single storey rear extensions, many loft dormers, low decking and most garden rooms fall under it. Conservation areas, National Landscapes, Article 4 directions and conditions on newer estates can take those rights away.

Anything outside permitted development needs an application. For work to a house that's a householder application, with an eight week target for a decision once it's validated. A listed building needs listed building consent on top, for any work that affects its character, inside or out. Our guide to planning permission for extensions goes through the limits in detail.

a typical tile hung cottage
Illustration of a typical tile hung cottage. Not a real address.

What do Building Regulations cover?

Building Regulations set minimum standards for how building work is done. Schedule 1 of the 2010 Regulations splits them into parts, each with a letter. The ones that turn up on almost every house job are A (structure), B (fire safety), C (damp and site preparation), F (ventilation), H (drainage), K (stairs, guarding and glazing safety), L (energy) and P (electrical safety in homes).

They apply to building work, not to the planning idea of development. That includes putting up or extending a building, structural alterations, new drainage or heating, and replacing or renovating parts like roofs and windows. It doesn't matter whether you needed planning permission.

The government publishes Approved Documents to show how to meet each part. They're where the numbers live. Approved Document K sets the rules for stairs in homes: a maximum pitch of 42 degrees, each rise between 150mm and 220mm, and each going between 220mm and 300mm. Loft stairs normally need 2 metres of headroom. Where the roof won't allow it, 1.9 metres at the centre and 1.8 metres at the side can be accepted. Planning never asks about any of that. Building control always does.

Approved Documents aren't the only way to comply, but if you follow them you're on solid ground, and building control will expect a good reason if you don't.

One of our carpenters in a tool rig marking out a long length of C24 timber on trestles inside a loft
Marking out C24 timber inside a loft conversion. The stair and the new floor are Building Regulations work.

Common jobs: which need planning, which need Building Regulations

A starting point for an ordinary house that still has its permitted development rights. Designated land, listed buildings and removed rights can change the planning column.

JobPlanning permissionBuilding Regulations
Single storey rear extension within the limitsUsually not: permitted developmentYes
Two storey or side extension beyond the limitsYes, a householder applicationYes
Loft conversion with a rear dormerOften not: permitted development up to 40 or 50 cubic metresYes
Dormer on a front roof slope facing a roadYesYes
Knocking through a load-bearing wallNo, unless the house is listedYes, it's structural work
Converting an integral garage into a roomUsually not, if nothing is enlarged and no condition removed the rightYes
Replacement windowsUsually not, except on listed buildings or under an Article 4 directionYes, usually self-certified by a registered installer
Re-covering a flat roofNoYes, and replacing more than half usually means upgrading the insulation
New kitchen in the same roomNoNot for a like-for-like refit; a new circuit, moved drains or a wall coming out can bring it in
Garden room under 15 square metres, no bedroomUsually not, within the height and position limitsNo
Garden room of 15 to 30 square metres, no bedroomUsually not, within the limitsNo, if it's at least 1 metre from the boundary or built mostly of non-combustible material
Decking no more than 30 centimetres highUsually not, within the half-the-garden ruleUsually not
Decking over 30 centimetres highYes, it counts as a raised platformUsually not
Porch of 3 square metres or lessUsually not, if it's under 3 metres high and 2 metres back from a road boundaryUsually not: a ground level porch under 30 square metres is exempt

Building Regulations exemptions for small buildings and porches come from Schedule 2 of the Building Regulations 2010. Planning limits come from the GPDO 2015. Checked November 2026.

Who do you ask about each one?

Planning goes to your council. Every house has one local planning authority, your district or borough council, and its planning team decides applications, prior approvals and certificates. If you think a job is permitted development and want proof, ask the council for a lawful development certificate. It's optional, but it's a legal decision, and the paper a buyer's solicitor will usually want.

Building Regulations go to a building control body. You can use your council's building control team or a registered private building control approver. Private building control firms must now be registered with the Building Safety Regulator. You can check any firm on the government's public register.

Some work is self-certified. Replacement windows, electrics and heating are often done by installers registered with a competent person scheme, who sign off their own work and notify building control for you.

Some permissions belong to neither. Party wall notices go to your neighbours, consent to build near a public sewer comes from the water company, and work to protected trees needs the council's tree officer.

How planning and Building Regulations fit together on a job

On a typical extension or loft the two run one after the other, and the order matters.

  1. Design and survey. A measured survey and the planning drawings: what the thing looks like and how big it is.
  2. Planning. An application, prior approval or a lawful development certificate, or nothing if you're happy it's permitted development. Read the conditions on any permission. Some have to be cleared with the council before any work starts.
  3. Building Regulations drawings. Construction detail, the structural engineer's calculations and the specification. These are different drawings from the planning set, and a lot more detailed.
  4. Building control application. Either full plans, where the drawings are checked before you start, or a building notice, where you start on notice and the work is inspected as it goes. Full plans is the only option if you're building over or near a public sewer.
  5. Notices and inspections. Building control has to be told at least two days before work starts, again within five days of work starting, and again within five days of completion. It inspects at the stages in its plan, usually footings, drains, structure and insulation before they're covered.
  6. Completion certificate. Keep it with your planning paperwork. You'll need both when you sell.

The trap is assuming a planning approval means the design works. Planning drawings don't show the steel sizes, the stair headroom or the escape window. A design that sailed through planning can still need changing for Building Regulations, and the cheapest place to find that out is on paper.

Five mix-ups we hear on site

  • "It's permitted development, so there are no rules." Permitted development only covers planning. The extension still needs Building Regulations approval, inspections and a completion certificate.
  • "Planning approved the drawings, so we can build from them." Planning drawings show the outside. Nobody can price or build the structure from them.
  • "Building control signed it off, so the neighbours can't complain." Building control says nothing about planning. If the extension needed permission and didn't have it, the council's planning team can still act, and it's the owner it writes to.
  • "It's only a wall inside, nobody needs to know." Taking out a load-bearing wall is structural work. Work that doesn't meet Building Regulations can be ordered out for up to ten years after it's finished (Building Act 1984, section 36), and a missing certificate turns up when you sell.
  • "The builder deals with all of that." Partly true. Since October 2023 the law requires everyone designing or building your project to be competent for the work they take on, and to make sure it complies. When we're your only contractor, the client's Building Regulations and site safety duties pass to us by law. Planning permission stays with the land and its owner, though, so the application and its conditions are yours to keep an eye on.

What to have ready before you ask a builder to price it

With these in hand, a quote can be for the job you're actually allowed to build.

  • Whether the job needs planning permission, prior approval or neither, and any decision notice or certificate
  • The conditions on any planning permission, especially ones to clear before work starts
  • Whether the house is listed, in a conservation area or in a National Landscape
  • The drawings, and the structural engineer's calculations if there are any
  • Which building control route you plan to use, if you've chosen one
  • Where things stand with the neighbours on party wall notices
  • Photos of the house inside and out, and the part that's changing

What this means for your job

Ask two questions, not one. Does it need planning permission? And does it need Building Regulations approval? Most structural jobs need the second even when they don't need the first, and the second is where the money and the safety are.

We're carpenters who run building jobs, so most of our day sits on the Building Regulations side: joists to the engineer's sizes, stairs to Approved Document K, insulation that building control can see before it's covered. Send us what you've got, drawings or just photos, and we'll tell you which approvals we'd expect your job to need. Start with our building work page, or for smaller jobs, garden rooms and decking.

Sources

  1. legislation.gov.uk: Town and Country Planning Act 1990, section 55 (meaning of development)
  2. legislation.gov.uk: The Town and Country Planning (General Permitted Development) (England) Order 2015, Schedule 2, Part 1, checked November 2026
  3. Planning Portal: Extensions, planning permission, checked November 2026
  4. Planning Portal: Householder planning consent
  5. Planning Portal: Lawful development certificates
  6. legislation.gov.uk: The Building Regulations 2010, checked November 2026
  7. legislation.gov.uk: The Building Regulations 2010, Schedule 2 (exempt buildings and work)
  8. legislation.gov.uk: The Building Regulations 2010, regulations 12 and 16 (applications and notices)
  9. legislation.gov.uk: The Building Regulations 2010, Part 2A (dutyholders and competence)
  10. GOV.UK: Building regulations approval, checked November 2026
  11. GOV.UK: Building regulations approval, when you do not need approval
  12. GOV.UK: Find a registered building control approver in England
  13. GOV.UK: Approved Document K, protection from falling, collision and impact
  14. legislation.gov.uk: Building Act 1984, section 36 (removal or alteration of offending work)
  15. legislation.gov.uk: Planning (Listed Buildings and Conservation Areas) Act 1990, section 7